Salient Features
Sunkoshi Small Hydropower Project
| GENERAL INFORMATION | |
| Project Type | Run-of-River | 
| Installed Capacity | 2.60 MW | 
| Number of units | 2 | 
| Gross head | 124.50 m | 
| Net energy | 14.38 GWh | 
| HYDROLOGY | |
| Catchment area | 81.00 km² | 
| Average annual flow | 5.77 m³/s | 
| Design discharge | 2.7 m³/s | 
| Minimum monthly flow | 1.10 m³/s | 
| Compensation flow | 90.00 l/s | 
| Project design floods | |
| 20-years | 130.00 m³/s | 
| 100-years | 325.00 m³/s | 
| 500-years | 460.00 m³/s | 
| HEADWORKS | |
| Weir | |
| Weir length | 36m | 
| Weir crest level | 952.50 m amsl | 
| Weir height (Above river bed) | 2.00 m | 
| Weir discharge capacity | 368.00 m³/s | 
| Intake | |
| Bottom orifice sill level | 951.50 m amsl | 
| Intake orifice size | 1.50 m x 0.30 m (2 x 4 nos) | 
| Design discharge including gravel flushing and sediment flushing | 368.00 m³/s | 
| Maximum intake capacity | 8.00 m³/s | 
| Intake culvert | |
| Total length | 60.00 m | 
| Canal slope | 1 in 50 | 
| Size | 1.29 x 2.20 m with 0.25 m freeboard at 100 years flood | 
| Gravel trap | |
| Length (including transition) | 18.40 m | 
| Width | 4.00 m | 
| Settling length | 20.00 m | 
| Flushing discharge | 0.80 m³/s | 
| Flushing gate | 1 no. size 0.60m x 0.75m | 
| Particle size to be settled | 5mm | 
| Gravel flushing channel | |
| Type | Rectangular with hard stone lining | 
| Length | 12.50 m | 
| Width | 1.00 m x 1.50 m | 
| Slope | 1:35 | 
| Pipe Crossing | |
| Truss bridge length | 30.00 m | 
| Pipe crossing | 40 m long 1300 dia 6 mm thick MS pipe | 
| Approach canal | |
| Length | 220.00 m | 
| Size | 1.60 m x 1.50 m | 
| Slope | 1:530 | 
| Settling basin | |
| Length (including transition) | 77.00 m | 
| Settling chambers | 2 nos., 4.50 m wide each | 
| Settling length | 45.00 m | 
| Flushing discharge | 1.08 m³/s | 
| Particle size to be settled | 0.2 mm | 
| Particle trapping efficiency | 90% | 
| Sediment flushing gate size | 2 nos. 0.6m x 0.6m | 
| Sediment flushing channel | |
| Type | Rectangular | 
| Length | 23.00 m | 
| Size | 1.20 m x 1.00 m | 
| Slope | 1:30 | 
| Forebay | |
| Size | 10.00 m x 10.50 m x 5.60 m | 
| Pressure Pipe | |
| Type | Buried and exposed | 
| Material | GRP and mild steel | 
| Total length | 25.50 m | 
| Internal diameter | 1200mm and 1300mm | 
| POWERHOUSE | |
| Type | Surface | 
| Size | 18.00 m wide and 24.00 long | 
| Turbine axis level | 825.50 m amsl | 
| TAILRACE | |
| Type | Open canal structure | 
| Length | 43.00 m | 
| Tail water level | 819.00 m amsl | 
| ELECTRO-MECHANICAL EQUIPMENTS | |
| Turbine | |
| Turbine type | Turgo | 
| Model | XJA – 60A/2 x14.5 | 
| Number of units | 2 nos. | 
| Rated capacity | 1317 kW each | 
| Efficiency | 85% | 
| Turbine inlet valve | Gate valve | 
| Powerhouse crane | Overhead travelling crane | 
| Capacity | 10 tons | 
| Generator | |
| Model | SFW 1250-10/ 1430 | 
| Rated Output | 1250 kW each | 
| Rated frequency | 50 hz | 
| Rated Current | 143.2 A | 
| Rated Voltage | 6300 V | 
| Power factor | 0.8 | 
| Rated speed | 750 rpm | 
| Insulation Degree | F/F | 
| Main Transformer | |
| Model | S93150-11/6.3 | 
| Rated Capacity | 3150 kVA | 
| Voltage | 6.3 kV to 11 kV | 
| Service Power Transformer | |
| Model | S9-M-63/6kV | 
| Rated Capacity | 63 kVA | 
| Excitation Transformer | |
| Model | ZSJ-50/ 6 kVA | 
| Rated capacity | 50 kVA | 
| Transmission line | |
| Line length | 6.3km long, 11kV, single circuit | 
| Switchyard | 17 m x 15 m (approx.) | 
| POWER AND ENERGY | |
| Design discharge | 2.70 m³/s | 
| Gross head | 125.5 m | 
| Net head at full flow | 117.5 m | 
| Installed capcity | 2.6 MW | 
| Total energy per year | 14.38 GWh | 
| Power evacuation | At 11 kV Sunkoshi Substation, Phurketar, Lamosanghu, NEA HT switchboard 11 kV, 25 kA with copper Bus bar rated 2000 A consisting of incomer panel | 
